New construction of the upper arch bridge in the spa gardens

Following demolition work in January, the municipal council awarded contracts for the replacement superstructure and structural steel works at its meeting held on March 23, 2021. Etzel Bau from Bad Wildbad was commissioned to carry out the solid construction work at a bid price of around 48,000 euros.

The contract for the new steel bridge was awarded to Stahlbau Ott from Kirchheim unter Teck at a price of around 107,800 euros. The approximately 21 m long pedestrian bridge over the Nagold river connects the area to the west and is also a link to the SOPHI park. A total of 330,000 euros has been earmarked for the measure. The town received a grant of 140,500 euros from the State’s “Bridges” redevelopment fund. The new arch bridge is scheduled for completion by the end of June.

Ihren Wasserzählerstand einfach online erfassen.

Liebe Bürgerinnen und Bürger,

Sie können während der Ableseperiode (17.09.2021 - 15:10.2021) Ihre Zählerstände online an uns übermitteln. Bitte geben Sie zur Identifizierung zunächst Ihre Benutzerkennung bestehend aus Buchungszeichen und Zählernummer in den dafür vorgesehenen Feldern ein und drücken Sie dann den Schalter "Login". Ihre Daten werden selbstverständlich verschlüsselt über eine gesicherte Internetverbindung übertragen.

Die Website zum eingeben der Zählerstände finden Sie unter: https://www.ablesen.de/badliebenzell/